How contractors can recover damages due to COVID-19

Photo of Michael Benes
Michael Benes, CPA, CFF 

By Michael R. Benes, CPA, CFF, Partner, and Kevin P. Krueger, CPA, Senior Manager, Wipfli, LLP

The economic fallout of COVID-19 is forcing contractors to juggle their need to keep employees safe while at the same time keeping projects running efficiently.

That means, no matter how hard we try, there will inevitably be impacts to construction projects and contractors will need to submit requests for extras to recover damages. And, while COVID-19 seems to be changing almost everything, it hasn’t impacted the legal basis for claiming damages or the requirement of needing to link project damages with accounting records.

The ability to recover damages is dependent on two things. The first relates to having a legal basis for recovery and the second being able to link the damages to the event.

Image of Kevin Krueger
Kevin Krueger, CPA

WHAT CONTRACTORS NEED TO TRACK TO BE ELIGIBLE TO RECOVER

Contractor impacts caused by the current pandemic potentially include the following:

  1. Suspension of the work
  2. Termination of the work
  3. Equipment supply disruptions
  4. Late delivery of materials required to complete the work
  5. Partial delivery of materials required to complete the work
  6. Cancelled delivery of materials required to complete the work
  7. Lack of work force to proceed efficiently
  8. Labor productivity impacts caused by social distancing
  9. Labor productivity impacts caused by unavailability of complete crews and workforce caused by
    • Illness
    • Quarantine
    • Owner restrictions
    • Governmental restrictions
  10. Medically testing employees showing up for work and periodically during the day
  11. Supplier and subcontractor defaults/bankruptcy
  12. Demobilization and remobilization to project sites
  13. Price escalation upon restarting projects
  14. Standby mode costs
  15. Lack of timely site inspections by governmental agencies
  16. Project delay costs
  17. Acceleration and constructive acceleration

HOW TO PROVE CONTRACTOR IMPACTS

Contractor impacts will need to be proven with actual project and accounting records to support claimed damages.

The impacts should be evaluated on a project by project basis, and contractors should start collecting data now to prove the impact and damages you are currently incurring.

Waiting until after COVID-19 is over will create added expense and might not identify all of the specific impacts and costs.

Contractors should document, document, document what is happening on every project each and every day. Daily reports should describe the impacts each and every shift and each and every day.

This starts with making sure you have a solid basis of the current project status as far as percentage complete and costs incurred before any impacts occur. Pictures and videos of the project should be taken to document the work installed at the time of any impacts.

To the extent specific identifiable costs can be tracked separately, new cost codes should be established with expenses and labor charges being posted directly to the new cost code. As an example, the cost of testing employees for the virus and the time involved can and should be tracked contemporaneously in newly established cost codes.

Not all impacts will easily allow for discrete tracking in newly established cost codes.

Labor productivity impacts fall into this category and may require improved tracking of daily productivity and daily impacts on productivity.

A contractor may also have an obligation to mitigate their damages. If they are not able to obtain materials from one supplier can they prove they attempted to obtain materials from another supplier?

Documenting will not be enough alone. Contractors must also prove the legal right to recover the damages.

While future executive orders or legislation could change the process, for now, the first step is to discuss your situation with legal counsel to determine your rights of recovery for project impacts.

While many are discussing “force majeure” clauses, that generally does not allow contractors to recover damages.

Instead, contractors may find legal footing in other contract clauses. Contracts generally require notice be provided to preserve your rights to claim damages. The determination of legal recovery will be fact specific and job specific — so pull out all your contracts and start reviewing them.

Laws in the jurisdiction where your project is located or the laws governing your contract will also impact your basis for recovery and should be considered when giving notice of an impact to your project.

You should seek out legal counsel who can wade through your contracts and project information to assist in determining the best path under the law toward recovery of damages.

Contractors should also ask their insurance agents if there is potential recovery through various insurance policies. Business interruption insurance, builders risk (all risk) insurance and delayed start up insurance are a few of the policies that might provide options for damage recovery.

FUTURE CONTRACTS

If you have any pending contracts, you might want to consider adding language regarding government-required quarantines or shelter-in-place orders. You might also consider covering material and equipment availability, and delivery impacts.

While we are currently in a never before seen situation and expect the construction industry will change in the future, we can be assured that one thing which will not change — the requirement to support recoverable damages with project and source accounting records.

The best time to document and collect your damages documentation starts now, when contemporaneous records can be collected and maintained.

Michael Benes can be reached at 414-431-9306. Kevin Krueger, CPA, can be reached at 414-431-9330.

Recommended Articles
Safety (blog)

12/12/2024

‘Tis the Season (for Winter Safety!)
Apprenticeship (blog)

11/22/2024

Apprenticeship Skill Competition Showcases Success!
Legislative (blog)

11/09/2024

2024 Election Recap